Bid evaluation
![]() |
This article should be read alongside Tender evaluation.
A tender, or 'bid' is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods and/or services.
Bid evaluation is the process that takes place after the tender submission deadline. It involves the opening and examining of the bids to identify the preferred supplier(s) for the project. Negotiations may then be entered into with one or more suppliers, and the successful supplier awarded the contract.
NB: There may have been a pre-qualification process before bids were invited to reduce the number of potential tenders to those that are genuinely appropriate for the project,
Generally, bid evaluation will be carried out in accordance with evaluation criteria or a selection methodology specified in the invitation to tender. Criteria or other factors that were not included in the invitation to tender should not be used to evaluate bids, and ideally, the same evaluators should evaluate all bids.
Bidding parties should submit clear and well-organised bids, but nonetheless, a great deal of thoroughness is required in the bid evaluation process, to ensure that proposals are properly understood, bids are compliant with invitation to tender, no information is overlooked and that correct conclusions are reached.
An initial review of the offers received is generally undertaken to determine their responsiveness and conformity to the conditions in the invitation to tender documents. Non-compliant bids may be rejected (unless a compliant bid has also been submitted).
A more detailed evaluation of compliant bids may then be undertaken against a number of pass/fail criteria. A technical determination should be made to ascertain whether the bidder’s technical solution is feasible, appropriate and deliverable within certain requirements, i.e. safety and costs. If a consortium has submitted the bid, the proposed project management should be assessed to determine how cohesive it will be in terms of delivering the project.
See Tender evaluation for more information.
There are a number of criteria upon which a preferred bidder can be identified:
- Lowest price
- Most economically advantageous tender (MEAT)
- Mean value
- Exclusion of the extremes
See Contract award for more information.
While it is common for the lowest priced tender to be awarded the contract, other factors – such as relevant experience and the perceived quality of the solution – should also be taken into consideration, as the lowest price does not always result in the best long-term value.
It may be the case that after the initial review only one bid will be sufficiently compliant. The lack of compliance or lack of interest may be because of deficiencies in the tender documents. If this is the case, then the tender documents could be rectified and the tender procedure begun again.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Best value procurement.
- Bidder.
- Bid writer.
- Competitive tender.
- Construction contract.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Selection criteria.
- The benefits of e-procurement in construction.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
https://autocadfiles.com/amp/residential-house-apartment-design-in-autocad-file-download
Residential House apartment design in autocad file</a> Download file, Bed Room & other room architecture Furniture detail & all interior design, PArking lay-out & Side section & Stair detail.